- Operating capacity
- 230 MW
- Units
- 4
- Online since
- 1992
- CO₂ a year
- 1.6 Mt
Tjiwi Kimia Paper Mill power station is a 230 MW coal power plant in Mliriprowo, Jawa, Indonesia.
It has 4 units, which came online between 1992 and 2015. Its boilers are subcritical. It is owned mainly by PT Pabrik Kertas Tjiwi Kimia Tbk. Traced to the top of the ownership chain, its largest owner is PT APP Purinusa Ekapersada (60%). Global Energy Monitor estimates it emits about 1.6 million tonnes of CO₂ a year. By capacity it is the 47th largest of 121 operating coal plants in Indonesia.
- Owner
- PT Pabrik Kertas Tjiwi Kimia Tbk
PT Pabrik Kertas Tjiwi Kimia Tbk [100%]
- Parent company
- PT Pabrik Kertas Tjiwi Kimia Tbk [100.0%]
- Coordinates
- -7.4368, 112.4688 (exact)
- GEM plant ID
- L100000104805
Plant details
How this coal plant is built and run.
- Combustion technology
- Subcritical
- Coal source
- Domestic
- Captive plant
- Supplies pulp & paper industry (power)
Climate
Carbon dioxide from this plant, as estimated by Global Energy Monitor.
- CO₂ a year
- 1.57 Mt
- CO₂ over remaining life
- 17 Mt
- Capacity factor
- 64%
- Efficiency
- 28%
Million tonnes, operating units
Up to 24 more years of operation
Country average GEM assumes for its coal fleet, not this plant's own figure
From a heat rate of 12,015 Btu/kWh
Retirement and national pledges
- Planned retirement
- Not announced
- Coal phase-out pledge
- None recorded
- Net-zero target
- 2060in 34 years
No retirement date has been announced, so nothing yet ties the plant to Indonesia’s 2060 net-zero target. Pledges are national commitments recorded by Global Energy Monitor.
Timeline
When each unit started, retired, or is planned to retire.
- Operating
- Retired
- In development
- Until planned retirement
Who owns it
Direct owners, and the owners at the top of each chain, as a share of operating capacity.
Direct owners
- PT Pabrik Kertas Tjiwi Kimia Company100%
Ownership chain
- PT APP Purinusa Ekapersada Companyowns 59.7% of PT Pabrik Kertas Tjiwi Kimia
- PT Pabrik Kertas Tjiwi Kimia Companyowns 100% of this plant
Ultimately owned by
- PT APP Purinusa Ekapersada Company59.7%
- small shareholder(s) Unidentified owners40.3%
No share traced to a government or state body.
See every plant owned by
Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.
Units
4 units at this site.
| Unit | Capacity | Status | Start | Retired / planned | Technology | Coal | CO₂ a year |
|---|---|---|---|---|---|---|---|
| Unit 1 | 35 MW | Operating | 1992 | — | Subcritical | — | 0.25 Mt |
| Unit 2 | 35 MW | Operating | 1993 | — | Subcritical | — | 0.25 Mt |
| Unit 3 | 70 MW | Operating | 1996 | — | — | — | 0.50 Mt |
| Unit 4 | 90 MW | Operating | 2015 | — | — | — | 0.57 Mt |
How it compares
Size among operating coal plants.
- In Asia
- 1,369th
- Age
- 34 yrs
of 1,872
Country average for coal: 13 yrs
44% of the average coal plant in Indonesia. About 4% of the size of the largest.
FAQ
About Tjiwi Kimia Paper Mill power station.
Who owns Tjiwi Kimia Paper Mill power station?
Its main owner is PT Pabrik Kertas Tjiwi Kimia Tbk. Traced to the top of each ownership chain, its owners are PT APP Purinusa Ekapersada (60%).
How big is Tjiwi Kimia Paper Mill power station?
It has 230 MW of operating capacity across 4 units. That makes it the 47th largest coal plant in Indonesia and the 1,774th largest in the world.
Where is Tjiwi Kimia Paper Mill power station?
In Mliriprowo, Jawa, Indonesia, at -7.4368, 112.4688.
When was Tjiwi Kimia Paper Mill power station built?
Its first unit started in 1992 and its newest in 2015.
How much CO₂ does Tjiwi Kimia Paper Mill power station emit?
Global Energy Monitor estimates about 1.6 million tonnes of CO₂ a year, and 17 million tonnes over the rest of its expected life.
Sources and identifiers
- Plant dataGlobal Energy Monitor, Global Coal Plant Tracker (2026-07) · GEM Wiki page
- OwnershipGlobal Energy Monitor, Global Energy Ownership Tracker, September 2026
- GEM plant IDL100000104805
Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.