Operating capacity
230 MW
Units
4
Online since
1992
CO₂ a year
1.6 Mt

Tjiwi Kimia Paper Mill power station is a 230 MW coal power plant in Mliriprowo, Jawa, Indonesia.

It has 4 units, which came online between 1992 and 2015. Its boilers are subcritical. It is owned mainly by PT Pabrik Kertas Tjiwi Kimia Tbk. Traced to the top of the ownership chain, its largest owner is PT APP Purinusa Ekapersada (60%). Global Energy Monitor estimates it emits about 1.6 million tonnes of CO₂ a year. By capacity it is the 47th largest of 121 operating coal plants in Indonesia.

Owner
PT Pabrik Kertas Tjiwi Kimia Tbk

PT Pabrik Kertas Tjiwi Kimia Tbk [100%]

Parent company
PT Pabrik Kertas Tjiwi Kimia Tbk [100.0%]
Coordinates
-7.4368, 112.4688 (exact)
GEM plant ID
L100000104805

Plant details

How this coal plant is built and run.

Combustion technology
Subcritical
Coal source
Domestic
Captive plant
Supplies pulp & paper industry (power)

Climate

Carbon dioxide from this plant, as estimated by Global Energy Monitor.

CO₂ a year
1.57 Mt

Million tonnes, operating units

CO₂ over remaining life
17 Mt

Up to 24 more years of operation

Capacity factor
64%

Country average GEM assumes for its coal fleet, not this plant's own figure

Efficiency
28%

From a heat rate of 12,015 Btu/kWh

Retirement and national pledges

Planned retirement
Not announced
Coal phase-out pledge
None recorded
Net-zero target
2060in 34 years

No retirement date has been announced, so nothing yet ties the plant to Indonesia’s 2060 net-zero target. Pledges are national commitments recorded by Global Energy Monitor.

Timeline

When each unit started, retired, or is planned to retire.

  • Operating
  • Retired
  • In development
  • Until planned retirement

Who owns it

Direct owners, and the owners at the top of each chain, as a share of operating capacity.

Direct owners

Ownership chain

  1. PT APP Purinusa Ekapersada Companyowns 59.7% of PT Pabrik Kertas Tjiwi Kimia
  2. PT Pabrik Kertas Tjiwi Kimia Companyowns 100% of this plant

Ultimately owned by

No share traced to a government or state body.

Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.

Units

4 units at this site.

UnitCapacityStatusStartRetired / plannedTechnologyCoalCO₂ a year
Unit 1 35 MW Operating 1992—Subcritical—0.25 Mt
Unit 2 35 MW Operating 1993—Subcritical—0.25 Mt
Unit 3 70 MW Operating 1996———0.50 Mt
Unit 4 90 MW Operating 2015———0.57 Mt

How it compares

Size among operating coal plants.

In Indonesia
47th

of 121 coal plants · see all

In Asia
1,369th

of 1,872

In the world
1,774th

of 2,643 · largest coal plants

Age
34 yrs

Country average for coal: 13 yrs

This plantTjiwi Kimia Paper Mill power station
230 MW
Average coal plantIn Indonesia, across 121 plants
518 MW
Largest in IndonesiaBanten Suralaya power station
6.0 GW

44% of the average coal plant in Indonesia. About 4% of the size of the largest.

FAQ

About Tjiwi Kimia Paper Mill power station.

Who owns Tjiwi Kimia Paper Mill power station?

Its main owner is PT Pabrik Kertas Tjiwi Kimia Tbk. Traced to the top of each ownership chain, its owners are PT APP Purinusa Ekapersada (60%).

How big is Tjiwi Kimia Paper Mill power station?

It has 230 MW of operating capacity across 4 units. That makes it the 47th largest coal plant in Indonesia and the 1,774th largest in the world.

Where is Tjiwi Kimia Paper Mill power station?

In Mliriprowo, Jawa, Indonesia, at -7.4368, 112.4688.

When was Tjiwi Kimia Paper Mill power station built?

Its first unit started in 1992 and its newest in 2015.

How much CO₂ does Tjiwi Kimia Paper Mill power station emit?

Global Energy Monitor estimates about 1.6 million tonnes of CO₂ a year, and 17 million tonnes over the rest of its expected life.

Sources and identifiers

Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.