Global Power Plant Directory121,919 plants · 219 countries & territories

All plants / China / Guangxi

Nanning Liujing Cogen power station

南宁市六景工业园区公共热电联产项目

Biomass CoalOperatingSubcritical

Nanning · Guangxi · China

Operating capacity
230 MW
Units
6
Online since
2024
CO₂ a year
0.2 Mt

Nanning Liujing Cogen power station is a 230 MW bioenergy power plant in Nanning, Guangxi, China.

It has 6 units, which came online between 2024 and 2025. Its boilers are subcritical. It is owned mainly by Nanning Sun Paper Co Ltd. Traced to the top of the ownership chain, its largest owner is Shandong SUN Paper (100%). Global Energy Monitor estimates it emits about 0.2 million tonnes of CO₂ a year. By capacity it is the 5th largest of 362 operating bioenergy plants in China.

Owner
Nanning Sun Paper Co Ltd

Nanning Sun Paper Co Ltd [100%]

Parent company
Shandong SUN Paper Co Ltd [100.0%]
In development
100 MW
Coordinates
22.8428, 108.9101 (exact)
GEM plant ID
L100000104926

Plant details

How this bioenergy plant is built and run.

Combustion technology
Subcritical
Coal source
Domestic/imported
Combined heat and power
Yes
Captive plant
Supplies industrial park industry (power and heat)
Permit
July 23, 2022

Climate

Carbon dioxide from this plant, as estimated by Global Energy Monitor.

CO₂ a year
0.24 Mt

Million tonnes, operating units

CO₂ over remaining life
8 Mt

Up to 33 more years of operation

Capacity factor
52%

Country average GEM assumes for its coal fleet, not this plant's own figure

Efficiency
33%

From a heat rate of 10,442 Btu/kWh

If new units are built
17 Mt

Lifetime CO₂ of units in development

Retirement and national pledges

Planned retirement
Not announced
Coal phase-out pledge
None recorded
Net-zero target
2060in 34 years

No retirement date has been announced, so nothing yet ties the plant to China’s 2060 net-zero target. Pledges are national commitments recorded by Global Energy Monitor.

Timeline

When each unit started, retired, or is planned to retire.

  • Operating
  • Retired
  • In development
  • Until planned retirement

Who owns it

Direct owners, and the owners at the top of each chain, as a share of operating capacity.

Direct owners

Ownership chain

  1. Shandong SUN Paper Companyowns 100% of Nanning Sun Paper
  2. Nanning Sun Paper Companyowns 100% of this plant

Ultimately owned by

No share traced to a government or state body.

Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.

Units

6 units at this site.

UnitCapacityStatusStartRetired / plannedTechnologyCoalCO₂ a year
Phase I Unit 1 50 MW Operating 2024—Subcritical—0.24 Mt
1.0 80 MW Operating 2025——Bioenergy: paper mill wastes, bioenergy: wastewater and sewage sludge (solids or biogas)—
46054.0 50 MW Operating 2025——Bioenergy: paper mill wastes—
46055.0 50 MW Operating 2025——Bioenergy: paper mill wastes—
Phase II Unit 2 50 MW Pre-construction ——Subcritical——
Phase II Unit 3 50 MW Pre-construction ——Subcritical——

How it compares

Size among operating bioenergy plants.

In China
5th

of 362 bioenergy plants · see all

In Asia
8th

of 845

In the world
29th

of 2,786 · largest bioenergy plants

Age
2 yrs

Country average for bioenergy: 8 yrs

This plantNanning Liujing Cogen power station
230 MW
Average bioenergy plantIn China, across 362 plants
42 MW

5.5× the average bioenergy plant in China. About 43% of the size of the largest.

FAQ

About Nanning Liujing Cogen power station.

Who owns Nanning Liujing Cogen power station?

Its main owner is Nanning Sun Paper Co Ltd. Traced to the top of each ownership chain, its owners are Shandong SUN Paper (100%).

How big is Nanning Liujing Cogen power station?

It has 230 MW of operating capacity across 6 units. That makes it the 5th largest bioenergy plant in China and the 29th largest in the world.

Where is Nanning Liujing Cogen power station?

In Nanning, Guangxi, China, at 22.8428, 108.9101.

When was Nanning Liujing Cogen power station built?

Its first unit started in 2024 and its newest in 2025.

How much CO₂ does Nanning Liujing Cogen power station emit?

Global Energy Monitor estimates about 0.2 million tonnes of CO₂ a year, and 8 million tonnes over the rest of its expected life.

Sources and identifiers

Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.