All plants / China / Guizhou
Liupanshui Dawan Waste Coal power station
六盘水大湾低热值(CFB)煤电项目
Dawan Town · Zhongshan District · Liupanshui · Guizhou · China
- Operating capacity
- 660 MW
- Units
- 2
- Online since
- 2026
- CO₂ a year
- 2.6 Mt
Liupanshui Dawan Waste Coal power station is a 660 MW coal power plant in Dawan Town, Guizhou, China.
It has 2 units, online since 2026. Its boilers are subcritical, burning waste coal coal. It is owned mainly by China Energy Construction Group Investment Co Ltd. Traced to the top of the ownership chain, its largest owner is China Energy Engineering Group (45%). Global Energy Monitor estimates it emits about 2.6 million tonnes of CO₂ a year. By capacity it is the 653rd largest of 1,225 operating coal plants in China.
- Owner
- China Energy Construction Group Investment Co Ltd
China Energy Construction Group Investment Co Ltd [100%]
- Parent company
- China Energy Engineering Corp Ltd [100.0%]
- In development
- 660 MW (from 2025)
- Coordinates
- 26.7751, 104.6531 (exact)
- GEM plant ID
- L100000104986
Plant details
How this coal plant is built and run.
- Combustion technology
- Subcritical
- Coal type
- Waste coal
- Coal source
- Domestic · minemouth (next to the mine)
- Permit
- September 19, 2022
Climate
Carbon dioxide from this plant, as estimated by Global Energy Monitor.
- CO₂ a year
- 2.61 Mt
- CO₂ over remaining life
- 91 Mt
- Capacity factor
- 52%
- Efficiency
- 39%
- If new units are built
- 91 Mt
Million tonnes, operating units
Up to 35 more years of operation
Country average GEM assumes for its coal fleet, not this plant's own figure
From a heat rate of 8,702 Btu/kWh
Lifetime CO₂ of units in development
Retirement and national pledges
- Planned retirement
- Not announced
- Coal phase-out pledge
- None recorded
- Net-zero target
- 2060in 34 years
No retirement date has been announced, so nothing yet ties the plant to China’s 2060 net-zero target. Pledges are national commitments recorded by Global Energy Monitor.
Timeline
When each unit started, retired, or is planned to retire.
- Operating
- Retired
- In development
- Until planned retirement
Who owns it
Direct owners, and the owners at the top of each chain, as a share of operating capacity.
Direct owners
- China Energy Construction Group Investment Company100%
Ownership chain
- China Energy Engineering Group Companyowns 44.8% of China Energy Engineering
- China Energy Engineering Companyowns 100% of China Energy Construction Group Investment
- China Energy Construction Group Investment Companyowns 100% of this plant
Ultimately owned by
- China Energy Engineering Group Company44.8%
- China Energy Company30.1%
- small shareholder(s) Unidentified owners17.5%
- China Guoxin Holding Company6.4%
- Government of Hong Kong Company1.2%
No share traced to a government or state body.
See every plant owned by
Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.
Units
2 units at this site.
| Unit | Capacity | Status | Start | Retired / planned | Technology | Coal | CO₂ a year |
|---|---|---|---|---|---|---|---|
| Unit 2 | 660 MW | Under construction | 2025 | — | Subcritical | Waste coal | — |
| Unit 1 | 660 MW | Operating | 2026 | — | Subcritical | Waste coal | 2.61 Mt |
How it compares
Size among operating coal plants.
- In Asia
- 905th
- Age
- 0 yrs
of 1,872
Country average for coal: 16 yrs
63% of the average coal plant in China. About 9% of the size of the largest.
FAQ
About Liupanshui Dawan Waste Coal power station.
Who owns Liupanshui Dawan Waste Coal power station?
Its main owner is China Energy Construction Group Investment Co Ltd. Traced to the top of each ownership chain, its owners are China Energy Engineering Group (45%), China Energy (30%), China Guoxin Holding (6%) and Government of Hong Kong (1%).
How big is Liupanshui Dawan Waste Coal power station?
It has 660 MW of operating capacity across 2 units. That makes it the 653rd largest coal plant in China and the 1,127th largest in the world.
Where is Liupanshui Dawan Waste Coal power station?
In Dawan Town, Zhongshan District, Liupanshui, Guizhou, China, at 26.7751, 104.6531.
When was Liupanshui Dawan Waste Coal power station built?
It started operating in 2026.
How much CO₂ does Liupanshui Dawan Waste Coal power station emit?
Global Energy Monitor estimates about 2.6 million tonnes of CO₂ a year, and 91 million tonnes over the rest of its expected life.
Sources and identifiers
- Plant dataGlobal Energy Monitor, Global Coal Plant Tracker (2026-07) · GEM Wiki page
- OwnershipGlobal Energy Monitor, Global Energy Ownership Tracker, September 2026
- GEM plant IDL100000104986
Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.