All plants / Indonesia / Jawa
Banten Serang power station
Salira · Pulo Ampel · Serang · Jawa · Indonesia
- Operating capacity
- 660 MW
- Units
- 2
- Online since
- 2017
- CO₂ a year
- 3.2 Mt
Banten Serang power station is a 660 MW coal power plant in Salira, Jawa, Indonesia.
It has 2 units, online since 2017. Its boilers are supercritical. It is owned mainly by PT Lestari Banten Energi. Traced to the top of the ownership chain, its largest owner is Genting Power Holdings (55%). Global Energy Monitor estimates it emits about 3.2 million tonnes of CO₂ a year. By capacity it is the 26th largest of 121 operating coal plants in Indonesia.
- Owner
- PT Lestari Banten Energi
PT Lestari Banten Energi [100%]
- Parent company
- Genting Power Holdings Ltd [55.0%]; SDIC Power Holdings Co Ltd [40.0%]; PT Hero Inti Pratama [5.0%]
- Coordinates
- -5.8830, 106.0459 (exact)
- GEM plant ID
- L100000102698
Plant details
How this coal plant is built and run.
- Combustion technology
- Supercritical
- Coal source
- Domestic
Climate
Carbon dioxide from this plant, as estimated by Global Energy Monitor.
- CO₂ a year
- 3.15 Mt
- CO₂ over remaining life
- 82 Mt
- Capacity factor
- 64%
- Efficiency
- 41%
Million tonnes, operating units
Up to 26 more years of operation
Country average GEM assumes for its coal fleet, not this plant's own figure
From a heat rate of 8,409 Btu/kWh
Retirement and national pledges
- Planned retirement
- Not announced
- Coal phase-out pledge
- None recorded
- Net-zero target
- 2060in 34 years
No retirement date has been announced, so nothing yet ties the plant to Indonesia’s 2060 net-zero target. Pledges are national commitments recorded by Global Energy Monitor.
Timeline
When each unit started, retired, or is planned to retire.
- Operating
- Retired
- In development
- Until planned retirement
Who owns it
Direct owners, and the owners at the top of each chain, as a share of operating capacity.
Direct owners
- PT Lestari Banten Energi Company100%
Ownership chain
- Genting Power Holdings Companyowns 55% of PT Lestari Banten Energi
- PT Lestari Banten Energi Companyowns 100% of this plant
Ultimately owned by
- Genting Power Holdings Company55%
- SDIC Power Holdings Company40%
- PT Hero Inti Pratama Company5%
No share traced to a government or state body.
See every plant owned by
Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.
Units
2 units at this site.
| Unit | Capacity | Status | Start | Retired / planned | Technology | Coal | CO₂ a year |
|---|---|---|---|---|---|---|---|
| Unit 1 | 660 MW | Operating | 2017 | — | Supercritical | — | 3.15 Mt |
| Unit 2 | 660 MW | Cancelled | 2025 | — | Supercritical | — | — |
Electricity output
How much power this plant produces.
WRI Global Power Plant Database, 2013–2019.
- Latest annual output
- 3.6 TWh
- Capacity factor
- 62%
- Estimation method
- CAPACITY-FACTOR-V1
Estimated · 2017
Output as a share of running at full power all year
Show data table
| Year | Reported (GWh) | Estimated (GWh) | Capacity factor | Method |
|---|---|---|---|---|
| 2013 | — | — | — | NO-ESTIMATION |
| 2014 | — | — | — | NO-ESTIMATION |
| 2015 | — | — | — | NO-ESTIMATION |
| 2016 | — | — | — | NO-ESTIMATION |
| 2017 | — | 3,591.70 | 62% | CAPACITY-FACTOR-V1 |
| 2018 | — | — | — | — |
| 2019 | — | — | — | — |
How it compares
Size among operating coal plants.
- In Asia
- 905th
- Age
- 9 yrs
of 1,872
Country average for coal: 13 yrs
1.3× the average coal plant in Indonesia. About 11% of the size of the largest.
FAQ
About Banten Serang power station.
Who owns Banten Serang power station?
Its main owner is PT Lestari Banten Energi. Traced to the top of each ownership chain, its owners are Genting Power Holdings (55%), SDIC Power Holdings (40%) and PT Hero Inti Pratama (5%).
How big is Banten Serang power station?
It has 660 MW of operating capacity across 2 units. That makes it the 26th largest coal plant in Indonesia and the 1,127th largest in the world.
Where is Banten Serang power station?
In Salira, Pulo Ampel, Serang, Jawa, Indonesia, at -5.8830, 106.0459.
When was Banten Serang power station built?
It started operating in 2017.
How much CO₂ does Banten Serang power station emit?
Global Energy Monitor estimates about 3.2 million tonnes of CO₂ a year, and 82 million tonnes over the rest of its expected life.
Sources and identifiers
- Plant dataGlobal Energy Monitor, Global Coal Plant Tracker (2026-07) · GEM Wiki page
- OwnershipGlobal Energy Monitor, Global Energy Ownership Tracker, September 2026
- Output 2013–2019WRI Global Power Plant Database v1.3.0 · WRI1075800
- GEM plant IDL100000102698
Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.