Global Power Plant Directory121,919 plants · 219 countries & territories

Companies / Governments and state bodies / China

State body

Shenzhen State-Owned Assets Supervision and Administration Commission of the State Council

深圳市国 资委

Owned operating capacity
5.6 GW
Operating plants
15
In development
5.7 GW
Countries
2
Global rank
#365

Shenzhen State-Owned Assets Supervision and Administration Commission of the State Council is recorded by Global Energy Monitor as a state body in China. Counting direct and indirect stakes, its share of operating coal, oil and gas and bioenergy power plants comes to 5.6 GW at 15 plants in 2 countries, ranking #365 of 13,356 owners on this site. 51% of that is coal, followed by gas (46%). Its largest holding is Heyuan power station in China, where its share of 42.5% equals 1.4 GW. The biggest part is held through Shenzhen Energy Group (about 5.6 GW). A further 5.7 GW is under construction, in pre-construction or announced. The capacity-weighted average age of its operating capacity is 11 years.

Fleet at a glance

Owned capacity by status, fuel and country.

By status

  • Operating5.6 GW44%
  • Under construction715 MW6%
  • Pre-construction1.1 GW8%
  • Announced3.9 GW31%
  • Retired405 MW3%
  • Cancelled1.1 GW8%

Operating, by fuel

  • Coal2.8 GW51%
  • Gas2.6 GW46%
  • Waste165 MW3%

Operating, by country

Operating capacity by decade it started · average age 11 years

1990s: 417 MW1990s417 MW2000s: 1.5 GW2000s1.5 GW2010s: 1.1 GW2010s1.1 GW2020s: 2.5 GW2020s2.5 GW

Map

15 operating plants with a stake held by Shenzhen State-Owned Assets Supervision and Administration Commission of the State Council.

Compared with peers

Largest state body owners in China, by owned operating capacity.

Ownership structure

Who owns Shenzhen State-Owned Assets Supervision and Administration Commission of the State Council, and what it owns.

Owned by

GEM records no owner above Shenzhen State-Owned Assets Supervision and Administration Commission of the State Council in this release.

Owns 1 company

Power plants

19 plants with a stake, largest owned capacity first.

PlantCountryFuelStatusOwned shareOwned operatingPlant operating
Heyuan power stationGuangdong · indirect China Coal Operating 42.5% 1.4 GW 3.2 GW
Shenzhen Energy East power stationGuangdong · indirect China Gas Operating 43.9% 1.0 GW 2.4 GW
Mawan power stationGuangdong · indirect China Coal Operating 32.2% 632 MW 2.0 GW
Shenzhen Energy Fengda Gas Thermal power stationGuangdong · indirect China Gas Operating 42.4% 543 MW 1.3 GW
Shenzhen Energy Zhangyang Gas power stationGuangdong · indirect China Gas Operating 32.7% 373 MW 1.1 GW
Baoding Northwest Suburb power stationHebei · indirect China Coal Operating 43.9% 307 MW 700 MW
Nanning power stationGuangxi · indirect China Coal Operating 20.8% 274 MW 1.3 GW
Shenneng Korla power stationXinjiang · indirect China Coal Operating 32.6% 228 MW 700 MW
Xibaipo power stationHebei · indirect China Coal Operating 8.8% 211 MW 2.4 GW
Sunon Asogli power stationGreater Accra · indirect Ghana Gas Operating 26.3% 148 MW 560 MW
Chaozhou Shenzhen Energy Fengquan Lake High-tech Zone Gas-fired Thermal power plantGuangdong · indirect China Gas Operating 43.9% 88 MW 200 MW
Shenzhen Energy Chao'an power stationGuangdong · indirect China Gas Operating 43.9% 88 MW 200 MW
Guangdong Shenzhen Bao'an power stationGuangdong · indirect China Waste Operating 43.5% 86 MW 199 MW
Guangdong Shenzhen East power stationGuangdong · indirect China Waste Operating 43.5% 78 MW 180 MW
Shenzhen Energy Hongwan Gas power stationGuangdong · indirect China Gas Operating 5.5% 74 MW 1.4 GW
Guang'an Huaying power stationSichuan · indirect China Coal Announced 43.9% — 2.0 GW planned
Guangshen power stationGuangdong · indirect China Coal Announced 28.4% — 2.0 GW planned
Zhaoqing Gas Turbine Integrated Demonstration power stationGuangdong · indirect China Gas Pre-construction 28.4% — 1.7 GW planned
Guangdong Shajiao power complexGuangdong · indirect China Coal Shelved 3.9% — 5.2 GW planned

Pipeline

Units under construction, in pre-construction or announced.

UnitCountryFuelStatusPlanned startOwnedUnit size
Baoding Northwest Suburb power stationPhase II Unit 3 China CoalUnder construction 2025 290 MW660 MW
Mawan power stationReplace Unit 1 China CoalUnder construction 2027 213 MW660 MW
Mawan power stationReplace Unit 2 China CoalUnder construction 2027 213 MW660 MW
Shenzhen Energy Fengda Gas Thermal power station3-1 China GasPre-construction — 195 MW460 MW
Shenzhen Energy Fengda Gas Thermal power station3-3 China GasPre-construction — 195 MW460 MW
Shenzhen Energy Fengda Gas Thermal power station3-2 China GasPre-construction — 195 MW460 MW
Zhaoqing Gas Turbine Integrated Demonstration power station2 China GasPre-construction — 185 MW650 MW
Zhaoqing Gas Turbine Integrated Demonstration power station3 China GasPre-construction — 185 MW650 MW
Zhaoqing Gas Turbine Integrated Demonstration power station1-HGT260 China GasPre-construction — 114 MW400 MW
Guang'an Huaying power stationUnit 1 China CoalAnnounced — 439 MW1.0 GW
Guang'an Huaying power stationUnit 2 China CoalAnnounced — 439 MW1.0 GW
Shenzhen Energy East power station3-1 China GasAnnounced — 382 MW870 MW
Shenzhen Energy East power station3-2 China GasAnnounced — 382 MW870 MW
Shenzhen Energy East power station3-3 China GasAnnounced — 382 MW870 MW
Guangshen power stationUnit 1 China CoalAnnounced — 284 MW1.0 GW
Guangshen power stationUnit 2 China CoalAnnounced — 284 MW1.0 GW
Mawan power stationGas Unit 8 Phase Two China GasAnnounced 2029 235 MW730 MW
Mawan power stationGas Unit 10 China GasAnnounced 2033 216 MW670 MW
Mawan power stationGas Unit 11 China GasAnnounced 2033 216 MW670 MW
Mawan power stationGas Unit 9 China GasAnnounced 2033 216 MW670 MW
Shenzhen Energy Zhangyang Gas power station3 China GasAnnounced — 154 MW470 MW
Nanning power stationPhase II Unit 3 China CoalAnnounced 2017 137 MW660 MW
Nanning power stationPhase II Unit 4 China CoalAnnounced 2017 137 MW660 MW

Facts

Name
Shenzhen State-Owned Assets Supervision and Administration Commission of the State Council
Local name
深圳市国 资委
Type
State body
Headquarters
Guangdong Sheng, China
GEM entity ID
E100001000063

Questions

How much power plant capacity does Shenzhen State-Owned Assets Supervision and Administration Commission of the State Council own?

Weighted by its ownership share, Shenzhen State-Owned Assets Supervision and Administration Commission of the State Council owns 5.6 GW of operating coal, oil and gas and bioenergy capacity at 15 plants in 2 countries. A further 5.7 GW is in development and 405 MW has been retired. Solar, wind, hydro, nuclear and geothermal plants are not covered by the ownership data.

What is Shenzhen State-Owned Assets Supervision and Administration Commission of the State Council’s largest power plant?

Heyuan power station in China is its largest holding by owned operating capacity (1.4 GW, a 42.5% share).

Who owns Shenzhen State-Owned Assets Supervision and Administration Commission of the State Council?

Global Energy Monitor records no owner above Shenzhen State-Owned Assets Supervision and Administration Commission of the State Council in this release.

Is Shenzhen State-Owned Assets Supervision and Administration Commission of the State Council building new power plants?

Yes. Its share of units under construction, in pre-construction or announced is 5.7 GW, including 715 MW under construction.

Which fuels do Shenzhen State-Owned Assets Supervision and Administration Commission of the State Council’s power plants use?

coal 51%, gas 46%, waste-to-energy 3% of its owned operating capacity.

How these numbers work. Global Energy Monitor links each coal, oil and gas and bioenergy unit to its direct owners, and each company to its own owners. This page follows every chain and multiplies the shares, so an owner with 50% of a company that owns 40% of a 1,000 MW unit is credited 200 MW. Shares GEM could not identify are left out, never guessed. Solar, wind, hydro, nuclear and geothermal plants are not in the ownership data.

Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.