National Pension Scheme Authority is recorded by Global Energy Monitor as a state body in Zambia. Counting direct and indirect stakes, its share of operating coal, oil and gas and bioenergy power plants comes to 20 MW at 2 plants in 1 country, ranking #11,087 of 13,356 owners on this site. 80% of that is coal, followed by bioenergy (20%). Its largest holding is Maamba power station in Zambia, where its share of 5.3% equals 16 MW. The biggest part is held through ZCCM Investments Holdings (about 16 MW). A further 26 MW is under construction, in pre-construction or announced. The capacity-weighted average age of its operating capacity is 11 years.

Fleet at a glance

Owned capacity by status, fuel and country.

By status

  • Operating20 MW43%
  • Under construction16 MW34%
  • Pre-construction1.3 MW3%
  • Announced9.3 MW20%

Operating, by fuel

  • Coal16 MW80%
  • Biomass3.9 MW20%

Operating, by country

Map

2 operating plants with a stake held by National Pension Scheme Authority.

Compared with peers

Largest state body owners worldwide, by owned operating capacity.

Ownership structure

Who owns National Pension Scheme Authority, and what it owns.

Owned by

GEM records no owner above National Pension Scheme Authority in this release.

Owns 2 companies

Power plants

3 plants with a stake, largest owned capacity first.

PlantCountryFuelStatusOwned shareOwned operatingPlant operating
Maamba power stationSouthern · indirect Zambia Coal Operating 5.3% 16 MW 300 MW
Nakambala power stationSouthern · indirect Zambia Biomass Operating 9.7% 3.9 MW 40 MW
Vedanta Zambia power stationCopperbelt · indirect Zambia Coal Announced 3.1% — 300 MW planned

Pipeline

Units under construction, in pre-construction or announced.

UnitCountryFuelStatusPlanned startOwnedUnit size
Maamba power stationUnit 3 Zambia CoalUnder construction 2026 7.9 MW150 MW
Maamba power stationUnit 4 Zambia CoalUnder construction 2026 7.9 MW150 MW
Nakambala power station2.0 Zambia BiomassPre-construction — 1.3 MW13 MW
Vedanta Zambia power stationUnit 2 Zambia CoalAnnounced — 4.6 MW150 MW
Vedanta Zambia power stationUnit 1 Zambia CoalAnnounced — 4.6 MW150 MW

Facts

Name
National Pension Scheme Authority
Abbreviation
NAPSA
Type
State body
Publicly listed
No
Headquarters
Lusaka, Zambia
Registered in
Zambia
Legal Entity Identifier
not found
PermID
5042235505
GEM entity ID
E100001011015

Questions

How much power plant capacity does National Pension Scheme Authority own?

Weighted by its ownership share, National Pension Scheme Authority owns 20 MW of operating coal, oil and gas and bioenergy capacity at 2 plants in 1 countries. A further 26 MW is in development and 0.0 MW has been retired. Solar, wind, hydro, nuclear and geothermal plants are not covered by the ownership data.

What is National Pension Scheme Authority’s largest power plant?

Maamba power station in Zambia is its largest holding by owned operating capacity (16 MW, a 5.3% share).

Who owns National Pension Scheme Authority?

Global Energy Monitor records no owner above National Pension Scheme Authority in this release.

Is National Pension Scheme Authority building new power plants?

Yes. Its share of units under construction, in pre-construction or announced is 26 MW, including 16 MW under construction.

Which fuels do National Pension Scheme Authority’s power plants use?

coal 80%, bioenergy 20% of its owned operating capacity.

How these numbers work. Global Energy Monitor links each coal, oil and gas and bioenergy unit to its direct owners, and each company to its own owners. This page follows every chain and multiplies the shares, so an owner with 50% of a company that owns 40% of a 1,000 MW unit is credited 200 MW. Shares GEM could not identify are left out, never guessed. Solar, wind, hydro, nuclear and geothermal plants are not in the ownership data.

Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.