Operating capacity
1.1 GW
Units
6
Online since
2004
CO₂ a year
1.5 Mt

Yixing Xielian power station is a 1.1 GW gas power plant in Yixing, Jiangsu, China.

It has 6 units, which came online between 1995 and 2015. Its boilers are subcritical, burning bituminous coal. It is owned mainly by Jiangsu Guoxin Xielian Gas Thermal Power Co Ltd. Traced to the top of the ownership chain, its largest owner is Jiangsu Guoxin (39%). Global Energy Monitor estimates it emits about 1.5 million tonnes of CO₂ a year. By capacity it is the 50th largest of 470 operating gas plants in China.

Owner
Jiangsu Guoxin Xielian Gas Thermal Power Co Ltd

Jiangsu Guoxin Xielian Gas Thermal Power Co Ltd [100%]

Parent company
Jiangsu Guoxin Corp Ltd [51.0%]; Wuxi Guolian Development (Group) Co Ltd [27.3%]; Wuxi Guofa Capital Operation Co Ltd [12.9%]; Wuxi Huaguang Environmental Energy Group Co Ltd [4.8%]; Wuxi Commercial Mansion Grand Orient Co Ltd [4.0%]
Retired
120 MW (last in 2014)
Coordinates
31.3960, 119.8284 (exact)
GEM plant ID
L100000101050

Plant details

How this gas plant is built and run.

Combustion technology
Subcritical
Coal type
Bituminous
Coal source
Domestic
Combined heat and power
Yes
State ownership
71% · partial state-owned enterprise

Climate

Carbon dioxide from this plant, as estimated by Global Energy Monitor.

CO₂ a year
1.50 Mt

Million tonnes, operating units

CO₂ over remaining life
20 Mt

Up to 14 more years of operation

Capacity factor
52%

Country average GEM assumes for its coal fleet, not this plant's own figure

Efficiency
28%

From a heat rate of 12,183 Btu/kWh

Retirement and national pledges

Planned retirement
Not announced
Coal phase-out pledge
None recorded
Net-zero target
2060in 34 years

No retirement date has been announced, so nothing yet ties the plant to China’s 2060 net-zero target. Pledges are national commitments recorded by Global Energy Monitor.

Timeline

When each unit started, retired, or is planned to retire.

  • Operating
  • Retired
  • In development
  • Until planned retirement

Who owns it

Direct owners, and the owners at the top of each chain, as a share of operating capacity.

Direct owners

Ownership chain

  1. Jiangsu Guoxin Companyowns 51% of Jiangsu Guoxin Xielian Gas Thermal Power
  2. Jiangsu Guoxin Xielian Gas Thermal Power Companyowns 75.7% of this plant

Ultimately owned by

At least 47.7% traced to a government or state body.

Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.

Units

6 units at this site.

UnitCapacityStatusStartRetired / plannedTechnologyCoalCO₂ a year
Unit 3 60 MW Retired 19952014SubcriticalBituminous—
Unit 4 60 MW Retired 19952014SubcriticalBituminous—
Unit 5 135 MW Operating 2004—SubcriticalBituminous0.75 Mt
Unit 6 135 MW Operating 2005—SubcriticalBituminous0.75 Mt
1 420 MW Operating 2015—Combined cycleFossil gas: natural gas—
2 420 MW Operating 2015—Combined cycleFossil gas: natural gas—

Electricity output

How much power this plant produces.

WRI Global Power Plant Database, 2013–2019.

ReportedEstimated
Latest annual output
3.9 TWh

Estimated · 2017

Capacity factor
40%

Output as a share of running at full power all year

Estimation method
CAPACITY-FACTOR-V1
Show data table
YearReported (GWh)Estimated (GWh)Capacity factorMethod
2013 — — — NO-ESTIMATION
2014 — — — NO-ESTIMATION
2015 — — — NO-ESTIMATION
2016 — — — NO-ESTIMATION
2017 — 3,898.15 40% CAPACITY-FACTOR-V1
2018 — — — —
2019 — — — —

How it compares

Size among operating gas plants.

In China
50th

of 470 gas plants · see all

In Asia
256th

of 1,355

In the world
526th

of 5,616 · largest gas plants

Age
22 yrs

Country average for gas: 9 yrs

This plantYixing Xielian power station
1.1 GW
Average gas plantIn China, across 470 plants
434 MW
Largest in ChinaWangting power station
3.3 GW

2.6× the average gas plant in China. About 33% of the size of the largest.

FAQ

About Yixing Xielian power station.

Who owns Yixing Xielian power station?

Its main owner is Jiangsu Guoxin Xielian Gas Thermal Power Co Ltd. Traced to the top of each ownership chain, its owners are Jiangsu Guoxin (39%), State-owned Assets Supervision and Administration Commission of Wuxi Municipal People's Government (37%), People's Government of Jiangsu Province (9%) and Wuxi Huaguang Environmental Energy Group (5%).

How big is Yixing Xielian power station?

It has 1.1 GW of operating capacity across 6 units. That makes it the 50th largest gas plant in China and the 526th largest in the world.

Where is Yixing Xielian power station?

In Yixing, Wuxi, Jiangsu, China, at 31.3960, 119.8284.

When was Yixing Xielian power station built?

Its first unit started in 1995 and its newest in 2015.

How much CO₂ does Yixing Xielian power station emit?

Global Energy Monitor estimates about 1.5 million tonnes of CO₂ a year, and 20 million tonnes over the rest of its expected life.

Sources and identifiers

Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.