All plants / China / Xinjiang
Xinjiang Bortala Santai (Guodian) wind farm
国电新疆艾比湖流域开发博尔塔拉博乐三台风电场一期49.5MW发电工程
Sailimu Lake · Bole City · Bortala AP · Xinjiang · China
- Operating capacity
- 100 MW
- Units
- 2
- Online since
- 2014
- Age
- 12 yrs
Xinjiang Bortala Santai (Guodian) wind farm is a 100 MW wind power plant in Sailimu Lake, Xinjiang, China.
It has 2 units, which came online between 2014 and 2021. It is owned mainly by Guodian Power Xinjiang New Energy Development Co Ltd and operated by Guodian Xinjiang Aibi Lake Basin Development. By capacity it is the 1,761st largest of 5,128 operating wind plants in China.
- Owner
- Guodian Power Xinjiang New Energy Development Co Ltd
China Anergy Construction Group Co Ltd [10%]; Guodian Power Xinjiang New Energy Development Co Ltd [89%]
- Operator
- Guodian Xinjiang Aibi Lake Basin Development
- Coordinates
- 44.6415, 81.3892 (exact)
- GEM plant ID
- L100000904820
Plant details
How this wind plant is built and run.
- Installation
- Onshore
Timeline
When each unit started, retired, or is planned to retire.
- Operating
- Retired
- In development
- Until planned retirement
Units
2 units at this site.
| Unit | Capacity | Status | Start | Technology |
|---|---|---|---|---|
| 1.0 | 50 MW | Operating | 2014 | Onshore |
| 2.0 | 50 MW | Operating | 2021 | Onshore |
How it compares
Size among operating wind plants.
- In Asia
- 1,961st
- Age
- 12 yrs
of 6,249
Country average for wind: 8 yrs
About average for China. About 2% of the size of the largest.
FAQ
About Xinjiang Bortala Santai (Guodian) wind farm.
Who owns Xinjiang Bortala Santai (Guodian) wind farm?
Its main owner is Guodian Power Xinjiang New Energy Development Co Ltd. It is operated by Guodian Xinjiang Aibi Lake Basin Development.
How big is Xinjiang Bortala Santai (Guodian) wind farm?
It has 100 MW of operating capacity across 2 units. That makes it the 1,761st largest wind plant in China and the 3,558th largest in the world.
Where is Xinjiang Bortala Santai (Guodian) wind farm?
In Sailimu Lake, Bole City, Bortala AP, Xinjiang, China, at 44.6415, 81.3892.
When was Xinjiang Bortala Santai (Guodian) wind farm built?
Its first unit started in 2014 and its newest in 2021.
What kind of power plant is Xinjiang Bortala Santai (Guodian) wind farm?
It is a wind power plant using Onshore technology.
Sources and identifiers
- Plant dataGlobal Energy Monitor, Global Wind Power Tracker (2026-02) · GEM Wiki page
- GEM plant IDL100000904820
Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.