All plants / China / Shandong
Taiyang Mill power station
山东太阳纸业热电厂
17 Yanwuting St · Yanzhou District · Jining · Shandong · China
- Operating capacity
- 335 MW
- Units
- 10
- Online since
- 2008
- CO₂ a year
- 1.5 Mt
Taiyang Mill power station is a 335 MW coal power plant in 17 Yanwuting St, Shandong, China.
It has 10 units, which came online between 2008 and 2019. Its boilers are subcritical, burning waste coal coal. It is owned mainly by Shandong SUN Paper Co Ltd. Traced to the top of the ownership chain, its largest owner is Shandong SUN Paper (100%). Global Energy Monitor estimates it emits about 1.5 million tonnes of CO₂ a year. By capacity it is the 873rd largest of 1,225 operating coal plants in China.
- Owner
- Shandong SUN Paper Co Ltd
Shandong SUN Paper Co Ltd [100%]
- Parent company
- Shandong SUN Paper Co Ltd [100.0%]
- In development
- 50 MW
- Retired
- 90 MW (last in 2021)
- Coordinates
- 35.5345, 116.7983 (exact)
- GEM plant ID
- L100000101403
Plant details
How this coal plant is built and run.
- Combustion technology
- Subcritical, supercritical
- Coal type
- Waste coal
- Coal source
- Domestic · minemouth (next to the mine)
- Combined heat and power
- Yes
- Captive plant
- Supplies pulp & paper industry (power and heat)
Climate
Carbon dioxide from this plant, as estimated by Global Energy Monitor.
- CO₂ a year
- 1.47 Mt
- CO₂ over remaining life
- 30 Mt
- Capacity factor
- 52%
- Efficiency
- 30%
- If new units are built
- 8 Mt
Million tonnes, operating units
Up to 25 more years of operation
Country average GEM assumes for its coal fleet, not this plant's own figure
From a heat rate of 11,313 Btu/kWh
Lifetime CO₂ of units in development
Retirement and national pledges
- Planned retirement
- Not announced
- Coal phase-out pledge
- None recorded
- Net-zero target
- 2060in 34 years
No retirement date has been announced, so nothing yet ties the plant to China’s 2060 net-zero target. Pledges are national commitments recorded by Global Energy Monitor.
Timeline
When each unit started, retired, or is planned to retire.
- Operating
- Retired
- In development
- Until planned retirement
Who owns it
Direct owners, and the owners at the top of each chain, as a share of operating capacity.
Direct owners
- Shandong SUN Paper Company100%
See every plant owned by
Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.
Units
10 units at this site.
| Unit | Capacity | Status | Start | Retired / planned | Technology | Coal | CO₂ a year |
|---|---|---|---|---|---|---|---|
| Unit 04 | 75 MW | Operating | 2008 | — | Subcritical | Waste coal | 0.39 Mt |
| Unit 08 | 40 MW | Retired | 2008 | 2021 | Subcritical | Waste coal | — |
| Unit 09 | 50 MW | Retired | 2009 | 2021 | Subcritical | Waste coal | — |
| Unit 05 | 50 MW | Operating | 2010 | — | Subcritical | Waste coal | 0.26 Mt |
| Unit 06 | 50 MW | Operating | 2011 | — | Subcritical | Waste coal | 0.26 Mt |
| Unit 10 | 50 MW | Operating | 2015 | — | Subcritical | Waste coal | 0.26 Mt |
| Unit 07 | 60 MW | Operating | 2016 | — | Subcritical | Waste coal | 0.31 Mt |
| 1.0 | 50 MW | Operating | 2019 | — | — | Bioenergy: paper mill wastes, bioenergy: wastewater and sewage sludge (solids or biogas) | — |
| Unit 11 | 350 MW | Cancelled | — | — | Supercritical | — | — |
| Unit 12 | 50 MW | Pre-construction | — | — | Subcritical | Waste coal | — |
Electricity output
How much power this plant produces.
WRI Global Power Plant Database, 2013–2019.
- Latest annual output
- 1.7 TWh
- Capacity factor
- 56%
- Estimation method
- CAPACITY-FACTOR-V1
Estimated · 2017
Output as a share of running at full power all year
Show data table
| Year | Reported (GWh) | Estimated (GWh) | Capacity factor | Method |
|---|---|---|---|---|
| 2013 | — | — | — | NO-ESTIMATION |
| 2014 | — | — | — | NO-ESTIMATION |
| 2015 | — | — | — | NO-ESTIMATION |
| 2016 | — | — | — | NO-ESTIMATION |
| 2017 | — | 1,656.71 | 56% | CAPACITY-FACTOR-V1 |
| 2018 | — | — | — | — |
| 2019 | — | — | — | — |
How it compares
Size among operating coal plants.
- In Asia
- 1,224th
- Age
- 18 yrs
of 1,872
Country average for coal: 16 yrs
32% of the average coal plant in China. About 5% of the size of the largest.
FAQ
About Taiyang Mill power station.
Who owns Taiyang Mill power station?
Its main owner is Shandong SUN Paper Co Ltd. Traced to the top of each ownership chain, its owners are Shandong SUN Paper (100%).
How big is Taiyang Mill power station?
It has 335 MW of operating capacity across 10 units. That makes it the 873rd largest coal plant in China and the 1,582nd largest in the world.
Where is Taiyang Mill power station?
In 17 Yanwuting St, Yanzhou District, Jining, Shandong, China, at 35.5345, 116.7983.
When was Taiyang Mill power station built?
Its first unit started in 2008 and its newest in 2019.
How much CO₂ does Taiyang Mill power station emit?
Global Energy Monitor estimates about 1.5 million tonnes of CO₂ a year, and 30 million tonnes over the rest of its expected life.
Sources and identifiers
- Plant dataGlobal Energy Monitor, Global Coal Plant Tracker (2026-07) · GEM Wiki page
- OwnershipGlobal Energy Monitor, Global Energy Ownership Tracker, September 2026
- Output 2013–2019WRI Global Power Plant Database v1.3.0 · WRI1075733
- GEM plant IDL100000101403