Global Power Plant Directory121,919 plants · 219 countries & territories

All plants / Philippines / Calabarzon

Puting Bato power station

CoalOperatingSubcritical

Puting Bato West · Calaca · Batangas · Calabarzon · Philippines

Operating capacity
270 MW
Units
2
Online since
2015
CO₂ a year
1.8 Mt

Puting Bato power station is a 270 MW coal power plant in Puting Bato West, Calabarzon, Philippines.

It has 2 units, which came online between 2015 and 2016. Its boilers are subcritical. It is owned mainly by South Luzon Thermal Energy Corp. Traced to the top of the ownership chain, its largest owner is Insular Life Assurance (100%). Global Energy Monitor estimates it emits about 1.8 million tonnes of CO₂ a year. By capacity it is the 16th largest of 27 operating coal plants in the Philippines. Its last operating unit is due to retire in 2040.

Owner
South Luzon Thermal Energy Corp

South Luzon Thermal Energy Corp [100%]

Parent company
Insular Life Assurance Co Ltd [100.0%]
Coordinates
13.9193, 120.8261 (exact)
GEM plant ID
L100000103167

Plant details

How this coal plant is built and run.

Combustion technology
Subcritical
Coal source
Domestic

Climate

Carbon dioxide from this plant, as estimated by Global Energy Monitor.

CO₂ a year
1.76 Mt

Million tonnes, operating units

CO₂ over remaining life
25 Mt

Up to 14 more years of operation

Capacity factor
65%

Country average GEM assumes for its coal fleet, not this plant's own figure

Efficiency
30%

From a heat rate of 11,313 Btu/kWh

Retirement and national pledges

Planned retirement
2040in 14 years
Coal phase-out pledge
None recorded
Net-zero target
None recorded

No retirement date has been announced for the operating units. Pledges are national commitments recorded by Global Energy Monitor.

Timeline

When each unit started, retired, or is planned to retire.

  • Operating
  • Retired
  • In development
  • Until planned retirement

Who owns it

Direct owners, and the owners at the top of each chain, as a share of operating capacity.

Direct owners

Ownership chain

  1. Insular Life Assurance Companyowns 100% of South Luzon Thermal Energy
  2. South Luzon Thermal Energy Companyowns 100% of this plant

Ultimately owned by

No share traced to a government or state body.

Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.

Units

2 units at this site.

UnitCapacityStatusStartRetired / plannedTechnologyCoalCO₂ a year
Unit 1 135 MW Operating 20152040 plannedSubcritical—0.88 Mt
Unit 2 135 MW Operating 20162040 plannedSubcritical—0.88 Mt

Electricity output

How much power this plant produces.

WRI Global Power Plant Database, 2013–2019.

ReportedEstimated
Latest annual output
1.9 TWh

Estimated · 2017

Capacity factor
80%

Output as a share of running at full power all year

Estimation method
CAPACITY-FACTOR-V1
Show data table
YearReported (GWh)Estimated (GWh)Capacity factorMethod
2013 — — — NO-ESTIMATION
2014 — — — NO-ESTIMATION
2015 — — — NO-ESTIMATION
2016 — — — NO-ESTIMATION
2017 — 1,890.45 80% CAPACITY-FACTOR-V1
2018 — — — —
2019 — — — —

How it compares

Size among operating coal plants.

In the Philippines
16th

of 27 coal plants · see all

In Asia
1,301st

of 1,872

In the world
1,691st

of 2,643 · largest coal plants

Age
11 yrs

Country average for coal: 15 yrs

This plantPuting Bato power station
270 MW
Average coal plantIn the Philippines, across 27 plants
468 MW
Largest in the PhilippinesDinginin power station
1.3 GW

58% of the average coal plant in the Philippines. About 20% of the size of the largest.

FAQ

About Puting Bato power station.

Who owns Puting Bato power station?

Its main owner is South Luzon Thermal Energy Corp. Traced to the top of each ownership chain, its owners are Insular Life Assurance (100%).

How big is Puting Bato power station?

It has 270 MW of operating capacity across 2 units. That makes it the 16th largest coal plant in the Philippines and the 1,691st largest in the world.

Where is Puting Bato power station?

In Puting Bato West, Calaca, Batangas, Calabarzon, Philippines, at 13.9193, 120.8261.

When was Puting Bato power station built?

Its first unit started in 2015 and its newest in 2016.

How much CO₂ does Puting Bato power station emit?

Global Energy Monitor estimates about 1.8 million tonnes of CO₂ a year, and 25 million tonnes over the rest of its expected life.

Sources and identifiers

Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.