Global Power Plant Directory121,919 plants · 219 countries & territories

All plants / Brunei / Brunei-Muara

Pulau Muara Besar power station

CoalOperatingUnknown

Pulau Muara Besar · Brunei-Muara · Brunei

Operating capacity
220 MW
Units
4
Online since
2019
CO₂ a year
1.2 Mt

Pulau Muara Besar power station is a 220 MW coal power plant in Pulau Muara Besar, Brunei-Muara, Brunei.

It has 4 units, online since 2019. It is owned mainly by Hengyi Industrial (Brunei) Co Ltd. Traced to the top of the ownership chain, its largest owner is Government of Brunei (30%). Global Energy Monitor estimates it emits about 1.2 million tonnes of CO₂ a year.

Owner
Hengyi Industrial (Brunei) Co Ltd

Hengyi Industrial (Brunei) Co Ltd [100%]

Parent company
Zhejiang HENGYI Group Co Ltd [42.1%]; Damai Holding Ltd [30.0%]; Hangzhou Wanyong Industrial Investment Co Ltd [18.9%]; unknown [8.9%]
Coordinates
5.0006, 115.1230 (exact)
GEM plant ID
L100000104551

Plant details

How this coal plant is built and run.

Coal source
Imported
Captive plant
Supplies chemicals industry (power)
State ownership
30% · partial state-owned enterprise

Climate

Carbon dioxide from this plant, as estimated by Global Energy Monitor.

CO₂ a year
1.15 Mt

Million tonnes, operating units

CO₂ over remaining life
32 Mt

Up to 28 more years of operation

Capacity factor
57%

Country average GEM assumes for its coal fleet, not this plant's own figure

Efficiency
33%

From a heat rate of 10,326 Btu/kWh

Retirement and national pledges

Planned retirement
Not announced
Coal phase-out pledge
None recorded
Net-zero target
2050in 24 years

No retirement date has been announced, so nothing yet ties the plant to Brunei’s 2050 net-zero target. Pledges are national commitments recorded by Global Energy Monitor.

Timeline

When each unit started, retired, or is planned to retire.

  • Operating
  • Retired
  • In development
  • Until planned retirement

Who owns it

Direct owners, and the owners at the top of each chain, as a share of operating capacity.

Direct owners

Ownership chain

  1. natural person(s) Individualsowns 60.2% of Zhejiang HENGYI Group
  2. Zhejiang HENGYI Group Companyowns 100% of Hong Kong Tianyi International Holding
  3. Hong Kong Tianyi International Holding Companyowns 70% of Hengyi Industrial (Brunei)
  4. Hengyi Industrial (Brunei) Companyowns 100% of this plant

Ultimately owned by

At least 30% traced to a government or state body.

Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.

Units

4 units at this site.

UnitCapacityStatusStartRetired / plannedTechnologyCoalCO₂ a year
Unit 1 55 MW Operating 2019———0.29 Mt
Unit 2 55 MW Operating 2019———0.29 Mt
Unit 3 55 MW Operating 2019———0.29 Mt
Unit 4 55 MW Operating 2019———0.29 Mt

FAQ

About Pulau Muara Besar power station.

Who owns Pulau Muara Besar power station?

Its main owner is Hengyi Industrial (Brunei) Co Ltd. Traced to the top of each ownership chain, its owners are Government of Brunei (30%).

How big is Pulau Muara Besar power station?

It has 220 MW of operating capacity across 4 units.

Where is Pulau Muara Besar power station?

In Pulau Muara Besar, Brunei-Muara, Brunei, at 5.0006, 115.1230.

When was Pulau Muara Besar power station built?

It started operating in 2019.

How much CO₂ does Pulau Muara Besar power station emit?

Global Energy Monitor estimates about 1.2 million tonnes of CO₂ a year, and 32 million tonnes over the rest of its expected life.

Sources and identifiers

Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.