Global Power Plant Directory121,919 plants · 219 countries & territories

All plants / Bangladesh / Dhaka

PowerPac Keraniganj power station

Oil GasOperatingInternal combustion

Dhaka · Bangladesh

Operating capacity
108 MW
Units
2
Online since
2012
Age
14 yrs

PowerPac Keraniganj power station is a 108 MW oil power plant in Dhaka, Bangladesh.

It has 2 units, online since 2012. It uses internal combustion technology burning heavy fuel oil, fossil gas: natural gas. It is owned mainly by PowerPac Holdings Ltd. Traced to the top of the ownership chain, its largest owner is Sikder Group (100%). By capacity it is the 34th largest of 73 operating oil plants in Bangladesh.

Owner
PowerPac Holdings Ltd

PowerPac Holdings Ltd [100%]

Parent company
Sikder Group [100.0%]
Coordinates
23.6479, 90.3477 (exact)
GEM plant ID
L100000408372

Plant details

How this oil plant is built and run.

Technology
Internal combustion
Fuel
Fossil liquids: heavy fuel oil, fossil gas: natural gas, fossil liquids: heavy fuel oil
Fuel classification
Multi Fuel, Oil

Who owns it

Direct owners, and the owners at the top of each chain, as a share of operating capacity.

Direct owners

Ownership chain

  1. Sikder Group Companyowns 100% of PowerPac Holdings
  2. PowerPac Holdings Companyowns 100% of this plant

Ultimately owned by

No share traced to a government or state body.

Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.

Units

2 units at this site.

UnitCapacityStatusStartRetired / plannedTechnologyTurbine or engine
1 108 MW Operating 2012—Internal combustion—
2 160 MW Cancelled ——Internal combustion—

Electricity output

How much power this plant produces.

WRI Global Power Plant Database, 2013–2019.

ReportedEstimated
Latest annual output
315 GWh

Estimated · 2017

Capacity factor
33%

Output as a share of running at full power all year

Estimation method
CAPACITY-FACTOR-V1
Show data table
YearReported (GWh)Estimated (GWh)Capacity factorMethod
2013 — — — NO-ESTIMATION
2014 — — — NO-ESTIMATION
2015 — — — NO-ESTIMATION
2016 — — — NO-ESTIMATION
2017 — 314.55 33% CAPACITY-FACTOR-V1
2018 — — — —
2019 — — — —

How it compares

Size among operating oil plants.

In Bangladesh
34th

of 73 oil plants · see all

In Asia
159th

of 254

In the world
469th

of 2,600 · largest oil plants

Age
14 yrs

Country average for oil: 10 yrs

This plantPowerPac Keraniganj power station
108 MW
Average oil plantIn Bangladesh, across 73 plants
112 MW
Largest in BangladeshJhulda power plant
317 MW

About average for Bangladesh. About 34% of the size of the largest.

FAQ

About PowerPac Keraniganj power station.

Who owns PowerPac Keraniganj power station?

Its main owner is PowerPac Holdings Ltd. Traced to the top of each ownership chain, its owners are Sikder Group (100%).

How big is PowerPac Keraniganj power station?

It has 108 MW of operating capacity across 2 units. That makes it the 34th largest oil plant in Bangladesh and the 469th largest in the world.

Where is PowerPac Keraniganj power station?

In Dhaka, Bangladesh, at 23.6479, 90.3477.

When was PowerPac Keraniganj power station built?

It started operating in 2012.

How much electricity does PowerPac Keraniganj power station generate?

An estimated 315 GWh was generated in 2017, a capacity factor of 33%, according to the WRI Global Power Plant Database.

Sources and identifiers

Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.