Global Power Plant Directory121,919 plants · 219 countries & territories

All plants / Malaysia / Melaka

Pahlawan power station

GasOperatingCombined cycle

Tanjung Kling · Melaka · Malaysia

Operating capacity
322 MW
Units
1
Online since
1999
Age
27 yrs

Pahlawan power station is a 322 MW gas power plant in Tanjung Kling, Melaka, Malaysia.

It has been operating since 1999. It uses combined cycle technology burning natural gas. It is owned mainly by Pahlawan Power Sdn Bhd. Traced to the top of the ownership chain, its largest owner is PanOcean Management (100%). By capacity it is the 16th largest of 26 operating gas plants in Malaysia.

Owner
Pahlawan Power Sdn Bhd

Pahlawan Power Sdn Bhd [100%]

Parent company
Usaha Tegas Sdn Bhd [100.0%]
Coordinates
2.2238, 102.1519 (exact)
GEM plant ID
L100000405307

Plant details

How this gas plant is built and run.

Technology
Combined cycle
Fuel
Fossil gas: natural gas
Fuel classification
Gas

Who owns it

Direct owners, and the owners at the top of each chain, as a share of operating capacity.

Direct owners

Ownership chain

  1. PanOcean Management Companyowns 100% of Excorp Holdings
  2. Excorp Holdings Companyowns 100% of Pacific States Investment
  3. Pacific States Investment Companyowns 100% of Usaha Tegas
  4. Usaha Tegas Companyowns 100% of Tanjong Capital
  5. Tanjong Capital Companyowns 100% of Tanjong
  6. Tanjong Companyowns 100% of Pahlawan Power
  7. Pahlawan Power Companyowns 100% of this plant

Ultimately owned by

No share traced to a government or state body.

Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.

Electricity output

How much power this plant produces.

WRI Global Power Plant Database, 2013–2019.

ReportedEstimated
Latest annual output
1.6 TWh

Estimated · 2017

Capacity factor
57%

Output as a share of running at full power all year

Estimation method
CAPACITY-FACTOR-V1
Show data table
YearReported (GWh)Estimated (GWh)Capacity factorMethod
2013 — — — NO-ESTIMATION
2014 — — — NO-ESTIMATION
2015 — — — NO-ESTIMATION
2016 — — — NO-ESTIMATION
2017 — 1,609.03 57% CAPACITY-FACTOR-V1
2018 — — — —
2019 — — — —

How it compares

Size among operating gas plants.

In Malaysia
16th

of 26 gas plants · see all

In Asia
716th

of 1,355

In the world
2,080th

of 5,616 · largest gas plants

Age
27 yrs

Country average for gas: 20 yrs

This plantPahlawan power station
322 MW
Average gas plantIn Malaysia, across 26 plants
670 MW
2.2 GW

48% of the average gas plant in Malaysia. About 14% of the size of the largest.

FAQ

About Pahlawan power station.

Who owns Pahlawan power station?

Its main owner is Pahlawan Power Sdn Bhd. Traced to the top of each ownership chain, its owners are PanOcean Management (100%).

How big is Pahlawan power station?

It has 322 MW of operating capacity. That makes it the 16th largest gas plant in Malaysia and the 2,080th largest in the world.

Where is Pahlawan power station?

In Tanjung Kling, Melaka, Malaysia, at 2.2238, 102.1519.

When was Pahlawan power station built?

It started operating in 1999.

How much electricity does Pahlawan power station generate?

An estimated 1.6 TWh was generated in 2017, a capacity factor of 57%, according to the WRI Global Power Plant Database.

Sources and identifiers

Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.