Coal GasOperatingSupercritical, subcritical, combined cycle

Böhlen · Leipzig · Sachsen · Germany

Operating capacity
1.9 GW
Units
5
Online since
1999
CO₂ a year
6.5 Mt

Lippendorf power station is a 1.9 GW coal power plant in Böhlen, Sachsen, Germany.

It has 5 units, which came online between 1969 and 2000. Its boilers are supercritical, burning lignite coal. It is owned mainly by EnBW Energie Baden-Württemberg AG. Traced to the top of the ownership chain, its largest owner is State of Baden-Württemberg (Germany) (47%). Global Energy Monitor estimates it emits about 6.5 million tonnes of CO₂ a year. By capacity it is the 6th largest of 57 operating coal plants in Germany. Its last operating unit is due to retire in 2035.

Owner
EnBW Energie Baden-Württemberg AG

EnBW Energie Baden-Württemberg AG [100%]

Parent company
EnBW Energie Baden-Württemberg AG [100.0%]
In development
875 MW (from 2029)
Retired
250 MW (last in 2000)
Coordinates
51.1845, 12.3729 (exact)
GEM plant ID
L100000101983

Plant details

How this coal plant is built and run.

Combustion technology
Supercritical, subcritical
Coal type
Lignite
Coal source
Domestic · minemouth (next to the mine)
Coal supply notes
United Schleenhain Coal Mine
Combined heat and power
Yes
State ownership
53% · partial state-owned enterprise

Climate

Carbon dioxide from this plant, as estimated by Global Energy Monitor.

CO₂ a year
6.50 Mt

Million tonnes, operating units

CO₂ over remaining life
59 Mt

Up to 9 more years of operation

Capacity factor
37%

Country average GEM assumes for its coal fleet, not this plant's own figure

Efficiency
34%

From a heat rate of 10,091 Btu/kWh

Retirement and national pledges

Planned retirement
2035in 9 years
Coal phase-out pledge
2038in 12 years
Net-zero target
2045in 19 years

The planned retirement comes 3 years before Germany’s coal phase-out date. Pledges are national commitments recorded by Global Energy Monitor.

Timeline

When each unit started, retired, or is planned to retire.

  • Operating
  • Retired
  • In development
  • Until planned retirement

Who owns it

Direct owners, and the owners at the top of each chain, as a share of operating capacity.

Direct owners

Ownership chain

  1. municipally owned Arrangementowns 100% of Zweckverband Oberschwäbische Elektrizitätswerke
  2. Zweckverband Oberschwäbische Elektrizitätswerke Companyowns 100% of OEW Energie-Beteiligungs
  3. OEW Energie-Beteiligungs Companyowns 47% of EnBW Energie Baden-Württemberg
  4. EnBW Energie Baden-Württemberg Companyowns 100% of this plant

Ultimately owned by

At least 47% traced to a government or state body.

Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.

Units

5 units at this site.

UnitCapacityStatusStartRetired / plannedTechnologyCoalCO₂ a year
Veag-C 100 MW Retired 19692000SubcriticalLignite—
Veag-IKW 150 MW Retired 19702000SubcriticalLignite—
Unit R 933 MW Operating 19992035 plannedSupercriticalLignite3.25 Mt
Unit S 933 MW Operating 20002035 plannedSupercriticalLignite3.25 Mt
CC1, timepoint 1 875 MW Pre-construction 20292040 plannedCombined cycleFossil gas: natural gas—

Electricity output

How much power this plant produces.

WRI Global Power Plant Database, 2013–2019.

ReportedEstimated
Latest annual output
4.3 TWh

Estimated · 2017

Capacity factor
26%

Output as a share of running at full power all year

Estimation method
CAPACITY-FACTOR-V1
Show data table
YearReported (GWh)Estimated (GWh)Capacity factorMethod
2013 — — — NO-ESTIMATION
2014 — — — NO-ESTIMATION
2015 — — — NO-ESTIMATION
2016 — — — NO-ESTIMATION
2017 — 4,301.81 26% CAPACITY-FACTOR-V1
2018 — — — —
2019 — — — —

How it compares

Size among operating coal plants.

In Germany
6th

of 57 coal plants · see all

In Europe
17th

of 197

In the world
361st

of 2,643 · largest coal plants

Age
27 yrs

Country average for coal: 37 yrs

This plantLippendorf power station
1.9 GW
Average coal plantIn Germany, across 57 plants
520 MW
Largest in GermanyBoxberg power station
2.6 GW

3.6× the average coal plant in Germany. About 72% of the size of the largest.

FAQ

About Lippendorf power station.

Who owns Lippendorf power station?

Its main owner is EnBW Energie Baden-Württemberg AG. Traced to the top of each ownership chain, its owners are State of Baden-Württemberg (Germany) (47%) and municipally owned (47%).

How big is Lippendorf power station?

It has 1.9 GW of operating capacity across 5 units. That makes it the 6th largest coal plant in Germany and the 361st largest in the world.

Where is Lippendorf power station?

In Böhlen, Leipzig, Sachsen, Germany, at 51.1845, 12.3729.

When was Lippendorf power station built?

Its first unit started in 1969 and its newest in 2000.

How much CO₂ does Lippendorf power station emit?

Global Energy Monitor estimates about 6.5 million tonnes of CO₂ a year, and 59 million tonnes over the rest of its expected life.

Sources and identifiers

  • Plant dataGlobal Energy Monitor, Global Coal Plant Tracker (2026-07) · GEM Wiki page
  • OwnershipGlobal Energy Monitor, Global Energy Ownership Tracker, September 2026
  • Output 2013–2019WRI Global Power Plant Database v1.3.0 · WRI1005619
  • GEM plant IDL100000101983
  • WEPP ID1116338
  • Beyond Fossil Fuels plant IDDE-155
  • Beyond Fossil Fuels unit IDDE-155-1