- Operating capacity
- 160 MW
- Units
- 2
- Online since
- 2020
- Age
- 6 yrs
Jianlong Xilin Gas power project is a 160 MW gas power plant in Xilin District, Heilongjiang, China.
It has 2 units, which came online between 2020 and 2021. It uses steam turbine technology burning industrial by-product: blast furnace gas, industrial by-product: coke oven gas. It is owned mainly by Jianlong Xilin Iron and Steel Co Ltd. By capacity it is the 252nd largest of 470 operating gas plants in China.
- Owner
- Jianlong Xilin Iron and Steel Co Ltd
Jianlong Xilin Iron and Steel Co Ltd [100%]
- Parent company
- Beijing Jianlong Investment Co Ltd [87.6%]; unknown [12.4%]
- Coordinates
- 47.5036, 129.2834 (exact)
- GEM plant ID
- L100001048141
Plant details
How this gas plant is built and run.
- Technology
- Steam turbine
- Fuel
- Industrial by-product: blast furnace gas, industrial by-product: coke oven gas
- Fuel classification
- Gas
- Captive plant
- Supplies iron & steel (power)
Timeline
When each unit started, retired, or is planned to retire.
- Operating
- Retired
- In development
- Until planned retirement
Who owns it
Direct owners, and the owners at the top of each chain, as a share of operating capacity.
Direct owners
- Jianlong Xilin Iron and Steel Company100%
Ownership chain
- natural person(s) Individualsowns 95.1% of Beijing Jianlong Investment
- Beijing Jianlong Investment Companyowns 94% of Beijing Jianlong Heavy Industry Group
- Beijing Jianlong Heavy Industry Group Companyowns 82.8% of Tianjin Jianlong Iron & Steel Industrial
- Tianjin Jianlong Iron & Steel Industrial Companyowns 100% of Zhejiang Jianlong Steel Industry
- Zhejiang Jianlong Steel Industry Companyowns 100% of Jilin Jianlong Steel
- Jilin Jianlong Steel Companyowns 100% of Shanxi Jianlong Steel Corporation,ltd
- Shanxi Jianlong Steel Corporation,ltd Companyowns 97% of Shanxi Jianlong Industrial
- Shanxi Jianlong Industrial Companyowns 100% of Jianlong Xilin Iron and Steel
- Jianlong Xilin Iron and Steel Companyowns 100% of this plant
Ultimately owned by
- natural person(s) Individuals87.5%
- Share not traceable12.5%
No share traced to a government or state body.
See every plant owned by
Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.
Units
2 units at this site.
| Unit | Capacity | Status | Start | Retired / planned | Technology | Turbine or engine |
|---|---|---|---|---|---|---|
| 1 | 80 MW | Operating | 2020 | — | Steam turbine | — |
| 2 | 80 MW | Operating | 2021 | — | Steam turbine | — |
How it compares
Size among operating gas plants.
- In Asia
- 942nd
- Age
- 6 yrs
of 1,355
Country average for gas: 9 yrs
37% of the average gas plant in China. About 5% of the size of the largest.
FAQ
About Jianlong Xilin Gas power project.
Who owns Jianlong Xilin Gas power project?
Its main owner is Jianlong Xilin Iron and Steel Co Ltd.
How big is Jianlong Xilin Gas power project?
It has 160 MW of operating capacity across 2 units. That makes it the 252nd largest gas plant in China and the 2,827th largest in the world.
Where is Jianlong Xilin Gas power project?
In Xilin District, Yichun, Heilongjiang, China, at 47.5036, 129.2834.
When was Jianlong Xilin Gas power project built?
Its first unit started in 2020 and its newest in 2021.
What kind of power plant is Jianlong Xilin Gas power project?
It is a gas power plant using steam turbine technology, fuelled by industrial by-product: blast furnace gas, industrial by-product: coke oven gas.
Sources and identifiers
- Plant dataGlobal Energy Monitor, Global Oil and Gas Plant Tracker (2026-08) · GEM Wiki page
- OwnershipGlobal Energy Monitor, Global Energy Ownership Tracker, September 2026
- GEM plant IDL100001048141