All plants / China / Heilongjiang
Heilongjiang Huachuan Storage Equipment Verification wind farm
桦川储能装备实证100MW风电项目
Huachuan · Jiamusi · Heilongjiang · China
- Operating capacity
- 100 MW
- Units
- 2
- Online since
- 2024
- Age
- 2 yrs
Heilongjiang Huachuan Storage Equipment Verification wind farm is a 100 MW wind power plant in Huachuan, Heilongjiang, China.
It has 2 units, online since 2024. It is owned mainly by Guoneng Heilongjiang New Energy Co Ltd and operated by Huachuan County China Energy Investment Langsheng New Energy. By capacity it is the 1,123rd largest of 5,128 operating wind plants in China.
- Owner
- Guoneng Heilongjiang New Energy Co Ltd
Guoneng Heilongjiang New Energy Co Ltd [80%]; Harbin Langsheng Electric Co Ltd [20%]
- Operator
- Huachuan County China Energy Investment Langsheng New Energy
- In development
- 100 MW
- Coordinates
- 47.0243, 130.7248 (approximate)
- GEM plant ID
- L100000919202
Plant details
How this wind plant is built and run.
- Installation
- Onshore
- Battery storage on site
- Yes
Units
2 units at this site.
| Unit | Capacity | Status | Start | Technology |
|---|---|---|---|---|
| 1.0 | 100 MW | Operating | 2024 | Onshore |
| 2.0 | 100 MW | Pre-construction | — | Onshore |
How it compares
Size among operating wind plants.
- In Asia
- 1,292nd
- Age
- 2 yrs
of 6,249
Country average for wind: 8 yrs
About average for China. About 2% of the size of the largest.
FAQ
About Heilongjiang Huachuan Storage Equipment Verification wind farm.
Who owns Heilongjiang Huachuan Storage Equipment Verification wind farm?
Its main owner is Guoneng Heilongjiang New Energy Co Ltd. It is operated by Huachuan County China Energy Investment Langsheng New Energy.
How big is Heilongjiang Huachuan Storage Equipment Verification wind farm?
It has 100 MW of operating capacity across 2 units. That makes it the 1,123rd largest wind plant in China and the 2,817th largest in the world.
Where is Heilongjiang Huachuan Storage Equipment Verification wind farm?
In Huachuan, Jiamusi, Heilongjiang, China, at 47.0243, 130.7248.
When was Heilongjiang Huachuan Storage Equipment Verification wind farm built?
It started operating in 2024.
What kind of power plant is Heilongjiang Huachuan Storage Equipment Verification wind farm?
It is a wind power plant using Onshore technology.
Sources and identifiers
- Plant dataGlobal Energy Monitor, Global Wind Power Tracker (2026-02) · GEM Wiki page
- GEM plant IDL100000919202
Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.