All plants / China / Guangdong
Haimen power station
华能汕头海门电厂
Haimen · Chaoyang · Shantou · Guangdong · China
- Operating capacity
- 4.1 GW
- Units
- 6
- Online since
- 2009
- CO₂ a year
- 17.1 Mt
Haimen power station is a 4.1 GW coal power plant in Haimen, Guangdong, China.
It has 6 units, which came online between 2009 and 2013. Its boilers are ultra-supercritical, burning bituminous coal. It is owned mainly by Huaneng Shantou Haimen Power Generation Co Ltd. Traced to the top of the ownership chain, its largest owner is Huaneng Power International (80%). Global Energy Monitor estimates it emits about 17.1 million tonnes of CO₂ a year. By capacity it is the 27th largest of 1,225 operating coal plants in China.
- Owner
- Huaneng Shantou Haimen Power Generation Co Ltd
Huaneng Shantou Haimen Power Generation Co Ltd [100%]
- Parent company
- Huaneng Power International Inc [80.0%]; Shantou Investment & Construction GENERAL Corp [20.0%]
- In development
- 2.1 GW (from 2026)
- Coordinates
- 23.1899, 116.6548 (exact)
- GEM plant ID
- L100000100381
Plant details
How this coal plant is built and run.
- Combustion technology
- Ultra-supercritical
- Coal type
- Bituminous
- Coal source
- Imported
- Combined heat and power
- Yes
- Permit
- September 1, 2006
- State ownership
- 20% · partial state-owned enterprise
Climate
Carbon dioxide from this plant, as estimated by Global Energy Monitor.
- CO₂ a year
- 17.14 Mt
- CO₂ over remaining life
- 347 Mt
- Capacity factor
- 52%
- Efficiency
- 37%
- If new units are built
- 273 Mt
Million tonnes, operating units
Up to 22 more years of operation
Country average GEM assumes for its coal fleet, not this plant's own figure
From a heat rate of 9,099 Btu/kWh
Lifetime CO₂ of units in development
Retirement and national pledges
- Planned retirement
- Not announced
- Coal phase-out pledge
- None recorded
- Net-zero target
- 2060in 34 years
No retirement date has been announced, so nothing yet ties the plant to China’s 2060 net-zero target. Pledges are national commitments recorded by Global Energy Monitor.
Timeline
When each unit started, retired, or is planned to retire.
- Operating
- Retired
- In development
- Until planned retirement
Who owns it
Direct owners, and the owners at the top of each chain, as a share of operating capacity.
Direct owners
- Huaneng Shantou Haimen Power Generation Company100%
Ownership chain
- Huaneng Power International Companyowns 100% of Huaneng (Guangdong) Energy Development
- Huaneng (Guangdong) Energy Development Companyowns 80% of Huaneng Shantou Haimen Power Generation
- Huaneng Shantou Haimen Power Generation Companyowns 100% of this plant
Ultimately owned by
- Huaneng Power International Company80%
- Shantou Municipal People's Government State-owned Assets Supervision and Administration Commission State body20%
At least 20% traced to a government or state body.
See every plant owned by
Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.
Units
6 units at this site.
| Unit | Capacity | Status | Start | Retired / planned | Technology | Coal | CO₂ a year |
|---|---|---|---|---|---|---|---|
| Phase I Unit 1 | 1.0 GW | Operating | 2009 | — | Ultra-supercritical | Bituminous | 4.29 Mt |
| Phase I Unit 2 | 1.0 GW | Operating | 2010 | — | Ultra-supercritical | Bituminous | 4.29 Mt |
| Phase I Unit 3 | 1.0 GW | Operating | 2013 | — | Ultra-supercritical | Bituminous | 4.29 Mt |
| Phase I Unit 4 | 1.0 GW | Operating | 2013 | — | Ultra-supercritical | Bituminous | 4.29 Mt |
| Phase II Unit 5 | 1.0 GW | Under construction | 2026 | — | Ultra-supercritical | Bituminous | — |
| Phase II Unit 6 | 1.0 GW | Under construction | 2027 | — | Ultra-supercritical | Bituminous | — |
Electricity output
How much power this plant produces.
WRI Global Power Plant Database, 2013–2019.
- Latest annual output
- 20.2 TWh
- Capacity factor
- 56%
- Estimation method
- CAPACITY-FACTOR-V1
Estimated · 2017
Output as a share of running at full power all year
Show data table
| Year | Reported (GWh) | Estimated (GWh) | Capacity factor | Method |
|---|---|---|---|---|
| 2013 | — | — | — | NO-ESTIMATION |
| 2014 | — | — | — | NO-ESTIMATION |
| 2015 | — | — | — | NO-ESTIMATION |
| 2016 | — | — | — | NO-ESTIMATION |
| 2017 | — | 20,192.43 | 56% | CAPACITY-FACTOR-V1 |
| 2018 | — | — | — | — |
| 2019 | — | — | — | — |
How it compares
Size among operating coal plants.
- In Asia
- 40th
- Age
- 17 yrs
of 1,872
Country average for coal: 16 yrs
4.0× the average coal plant in China. About 58% of the size of the largest.
FAQ
About Haimen power station.
Who owns Haimen power station?
Its main owner is Huaneng Shantou Haimen Power Generation Co Ltd. Traced to the top of each ownership chain, its owners are Huaneng Power International (80%) and Shantou Municipal People's Government State-owned Assets Supervision and Administration Commission (20%).
How big is Haimen power station?
It has 4.1 GW of operating capacity across 6 units. That makes it the 27th largest coal plant in China and the 43rd largest in the world.
Where is Haimen power station?
In Haimen, Chaoyang, Shantou, Guangdong, China, at 23.1899, 116.6548.
When was Haimen power station built?
Its first unit started in 2009 and its newest in 2013.
How much CO₂ does Haimen power station emit?
Global Energy Monitor estimates about 17.1 million tonnes of CO₂ a year, and 347 million tonnes over the rest of its expected life.
Sources and identifiers
- Plant dataGlobal Energy Monitor, Global Coal Plant Tracker (2026-07) · GEM Wiki page
- OwnershipGlobal Energy Monitor, Global Energy Ownership Tracker, September 2026
- Output 2013–2019WRI Global Power Plant Database v1.3.0 · WRI1070797
- GEM plant IDL100000100381
- WEPP ID1067312
Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.