All plants / Türkiye / Çanakkale
Cenal power station
Cenal Termik Santrali
Karabiga · Biga · Çanakkale · Türkiye
- Operating capacity
- 1.3 GW
- Units
- 3
- Online since
- 2017
- CO₂ a year
- 6.3 Mt
Cenal power station is a 1.3 GW coal power plant in Karabiga, Çanakkale, Türkiye.
It has 3 units, online since 2017. Its boilers are ultra-supercritical, burning bituminous coal. It is owned mainly by Cenal Elektrik AŞ. Global Energy Monitor estimates it emits about 6.3 million tonnes of CO₂ a year. By capacity it is the 3rd largest of 34 operating coal plants in Türkiye.
- Owner
- Cenal Elektrik AŞ
Cenal Elektrik AŞ [100%]
- Parent company
- Cengiz Holding AS [100.0%]
- In development
- 1.1 GW (from 2030)
- Coordinates
- 40.4167, 27.3183 (exact)
- GEM plant ID
- L100000103636
Plant details
How this coal plant is built and run.
- Combustion technology
- Ultra-supercritical
- Coal type
- Bituminous
- Coal source
- Imported
- Coal supply notes
- imported
Climate
Carbon dioxide from this plant, as estimated by Global Energy Monitor.
- CO₂ a year
- 6.30 Mt
- CO₂ over remaining life
- 164 Mt
- Capacity factor
- 66%
- Efficiency
- 41%
- If new units are built
- 180 Mt
Million tonnes, operating units
Up to 26 more years of operation
Country average GEM assumes for its coal fleet, not this plant's own figure
From a heat rate of 8,272 Btu/kWh
Lifetime CO₂ of units in development
Retirement and national pledges
- Planned retirement
- Not announced
- Coal phase-out pledge
- None recorded
- Net-zero target
- 2053in 27 years
No retirement date has been announced, so nothing yet ties the plant to Türkiye’s 2053 net-zero target. Pledges are national commitments recorded by Global Energy Monitor.
Timeline
When each unit started, retired, or is planned to retire.
- Operating
- Retired
- In development
- Until planned retirement
Who owns it
Direct owners, and the owners at the top of each chain, as a share of operating capacity.
Direct owners
- Cenal Elektrik Company100%
Ownership chain
- natural person(s) Individualsowns 100% of Cengiz Holding
- Cengiz Holding Companyowns 100% of Cengiz Enerji Sanayii ve Ticaret
- Cengiz Enerji Sanayii ve Ticaret Companyowns 100% of Bigacen Enerji Yatırımları
- Bigacen Enerji Yatırımları Companyowns 100% of Cenal Elektrik
- Cenal Elektrik Companyowns 100% of this plant
Ultimately owned by
- natural person(s) Individuals100%
No share traced to a government or state body.
See every plant owned by
Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.
Units
3 units at this site.
| Unit | Capacity | Status | Start | Retired / planned | Technology | Coal | CO₂ a year |
|---|---|---|---|---|---|---|---|
| Unit 1 | 660 MW | Operating | 2017 | — | Ultra-supercritical | Bituminous | 3.15 Mt |
| Unit 2 | 660 MW | Operating | 2017 | — | Ultra-supercritical | Bituminous | 3.15 Mt |
| Unit 3 | 1.1 GW | Pre-construction | 2030 | 2060 planned | — | — | — |
Electricity output
How much power this plant produces.
WRI Global Power Plant Database, 2013–2019.
- Latest annual output
- 7.4 TWh
- Capacity factor
- 64%
- Estimation method
- CAPACITY-FACTOR-V1
Estimated · 2017
Output as a share of running at full power all year
Show data table
| Year | Reported (GWh) | Estimated (GWh) | Capacity factor | Method |
|---|---|---|---|---|
| 2013 | — | — | — | NO-ESTIMATION |
| 2014 | — | — | — | NO-ESTIMATION |
| 2015 | — | — | — | NO-ESTIMATION |
| 2016 | — | — | — | NO-ESTIMATION |
| 2017 | — | 7,393.09 | 64% | CAPACITY-FACTOR-V1 |
| 2018 | — | — | — | — |
| 2019 | — | — | — | — |
How it compares
Size among operating coal plants.
- In Asia
- 394th
- Age
- 9 yrs
of 1,872
Country average for coal: 22 yrs
2.2× the average coal plant in Türkiye. About 47% of the size of the largest.
FAQ
About Cenal power station.
Who owns Cenal power station?
Its main owner is Cenal Elektrik AŞ.
How big is Cenal power station?
It has 1.3 GW of operating capacity across 3 units. That makes it the 3rd largest coal plant in Türkiye and the 509th largest in the world.
Where is Cenal power station?
In Karabiga, Biga, Çanakkale, Türkiye, at 40.4167, 27.3183.
When was Cenal power station built?
It started operating in 2017.
How much CO₂ does Cenal power station emit?
Global Energy Monitor estimates about 6.3 million tonnes of CO₂ a year, and 164 million tonnes over the rest of its expected life.
Sources and identifiers
- Plant dataGlobal Energy Monitor, Global Coal Plant Tracker (2026-07) · GEM Wiki page
- OwnershipGlobal Energy Monitor, Global Energy Ownership Tracker, September 2026
- Output 2013–2019WRI Global Power Plant Database v1.3.0 · WRI1075555
- GEM plant IDL100000103636
Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.