- Planned capacity
- 1.3 GW
- Units
- 3
- Expected online
- 2037
- Status
- Under construction
Abuja power station is a 1.3 GW gas power plant under construction in Gwagwalada, Abuja Federal Capital Territory, Nigeria.
It is expected to start operating in 2037. It uses combined cycle technology burning natural gas. It is owned mainly by NNPC Ltd. Traced to the top of the ownership chain, its largest owner is China National Machinery Industry (33%).
- Owner
- NNPC Ltd
NNPC Ltd [33%]; General Electric Co [33%]; China Machinery Engineering Corp [33%]
- Parent company
- China National Machinery Industry Corp [33.3%]; General Electric Co [33.3%]; NNPC Ltd [33.3%]
- In development
- 1.3 GW (from 2037)
- Coordinates
- 8.9397, 7.0768 (approximate)
- GEM plant ID
- L100000406772
Plant details
How this gas plant is built and run.
- Technology
- Combined cycle
- Fuel
- Fossil gas: natural gas
- Fuel classification
- Gas
- Turbine or engine
- GE Power: GT13E2, GE Power: GT13E2
Timeline
When each unit started, retired, or is planned to retire.
- Operating
- Retired
- In development
- Until planned retirement
Who owns it
Direct owners, and the owners at the top of each chain.
Direct owners
- NNPC Company33%
- General Electric Company33%
- China Machinery Engineering Company33%
Ownership chain
- Government of Nigeria Governmentowns 100% of Ministry of Finance Incorporated (Nigeria)
- Ministry of Finance Incorporated (Nigeria) State bodyowns 50% of NNPC
- NNPC Companyowns 33% of this plant
Ultimately owned by
- China National Machinery Industry Company33%
- Government of Nigeria Government33%
- small shareholder(s) Unidentified owners27.9%
- The Vanguard Group Company2.9%
- natural person(s) Individuals2%
- Share not traceable1%
At least 33% traced to a government or state body.
See every plant owned by
Source: Global Energy Monitor, Global Energy Ownership Tracker, September 2026 (CC BY 4.0). Capacity is weighted by each owner’s share.
Units
3 units at this site.
| Unit | Capacity | Status | Start | Retired / planned | Technology | Turbine or engine |
|---|---|---|---|---|---|---|
| 2 | 450 MW | Under construction | 2037 | — | Combined cycle | GE Power: GT13E2, GE Power: GT13E2 |
| 3 | 450 MW | Under construction | 2037 | — | Combined cycle | GE Power: GT13E2, GE Power: GT13E2 |
| 1 | 350 MW | Pre-construction | — | — | Combined cycle | GE Power: GT13E2, GE Power: GT13E2 |
FAQ
About Abuja power station.
Who owns Abuja power station?
Its main owner is NNPC Ltd. Traced to the top of each ownership chain, its owners are China National Machinery Industry (33%), Government of Nigeria (33%) and The Vanguard Group (3%).
How big is Abuja power station?
It is planned at 1.3 GW across 3 units.
Is Abuja power station operating yet?
Not yet. It is under construction and expected online in 2037.
Where is Abuja power station?
In Gwagwalada, Abuja, Abuja Federal Capital Territory, Nigeria, at 8.9397, 7.0768.
What kind of power plant is Abuja power station?
It is a gas power plant using combined cycle technology, fuelled by natural gas.
Sources and identifiers
- Plant dataGlobal Energy Monitor, Global Oil and Gas Plant Tracker (2026-08) · GEM Wiki page
- OwnershipGlobal Energy Monitor, Global Energy Ownership Tracker, September 2026
- GEM plant IDL100000406772
Licensed CC BY 4.0. Spotted an error? Plant data corrections go to Global Energy Monitor.